Facade refurbishment with external wall insulation, carried out on rope access.

La posa del cappotto termico in corda, senza ponteggio sull’intero fronte

Turin

Chanoux

Fitting the insulation boards on rope access, with no scaffolding across the whole elevation

Why rope access and not scaffolding

When what is missing is space on the ground — narrow courtyards, passages that must stay clear, access shared with the people who live there — full scaffolding would occupy the only way through for months. With rope access the site stays vertical: the crew works on two independent lines, one for work and one for safety, the boards go up one at a time and the ground floor stays clear.

Il cantiere visto dal cortile: lo spazio a terra è quello che decide la tecnica
The site seen from the courtyard: the space on the ground is what decides the technique

The work

Adhesive spread on the insulation board, fixed at height, then anchored. That is the part you see; the part that weighs is the planning, because on rope access the sequence of installation and the logistics of materials have to be decided beforehand and cannot be recovered halfway up a facade.

Stesura del collante: la lavorazione a terra prima della salita
Spreading the adhesive: the work on the ground before going up
Posa dei pannelli isolanti in quota
Fitting the insulation boards at height